Design-to-launch: control and audit worksheet

This worksheet lets you check whether a new product, service or variant passed through each gate between brief and launch with proper evidence, instead of being declared ready on enthusiasm. A manager or an outside reviewer fills it after each launch or at a midpoint of a long project, and the owner uses the findings to tighten the next one.

When to use it

Use it at the launch decision, after the first production lot or first customer batch, and when a launch went wrong or went late. It suits factories, workshops, food makers, clinics adding a new service and shops introducing their own label.

The template

GateWhat to checkEvidence to look atReviewerFindingCost impact in ₹
Brief approvedNeed, target customer, target selling price and deadline are written downSigned briefOwner
Specification fixedFinal specification matches the brief and has a version and dateSpecification sheetDesign lead
Sample testedSample passed the tests you decided before making itTest report, photosQuality lead
Cost signed offActual material and making cost is at or below the target costCosting sheet with quotesAccounts lead
Material and supplier readySupplier confirmed quantity, price and delivery datePurchase orders, supplier messagesPurchase lead
Staff trainedPeople who will make or sell it have been shown howTraining note with names and dateOperations head
Labels and licencesPack, label and any needed approval or licence are readyLabel proof, licence copiesOwner
Launch decisionA named person approved launch after seeing all the aboveLaunch approval noteOwner
First-month reviewResults compared with the briefReview noteOwner

How to fill it

  • What to check: change the wording to suit your product, but keep the check as something that can be proved with a paper.
  • Evidence to look at: write the document name, date and version you opened.
  • Finding: describe what you saw, for example "sample tested on 3 units only, brief asked for 10" or "costing uses an old rate".
  • Cost impact in ₹: estimate what the gap cost or could cost, such as rework, scrap or a delayed launch. Leave it blank only when there is really no money effect.
  • Labels and licences: for anything regulated, such as food, medicines, electrical goods or weights and measures, check the current rule on the official portal or with your CA before acting.

Example row

GateWhat to checkEvidence to look atReviewerFindingCost impact in ₹
Cost signed offActual cost within target of ₹140 per unitCosting sheet v3 dated 4 Oct 2026Accounts leadPackaging priced at ₹6 but supplier quote says ₹9.50; real cost ₹143.503,500 on first lot of 1,000

Review and sign-off

  • The reviewer signs each gate; the owner signs the completed worksheet and the launch decision separately.
  • Review at every launch, and mid-project for any project longer than a few months.
  • Escalate before launch when a gate has no evidence, when a sample failed and was changed without retesting, or when the cost is above target.

Keeping it up to date

  • Add a gate whenever a past launch problem shows a step that was missing.
  • Keep the findings and their fixes together so the next project can read them first.
  • Retain the worksheet, specification versions and test reports for the period your CA or the law requires.