Available to promise

Available to promise is the quantity of an item that can be committed to new customer orders, found from on-hand stock plus expected receipts minus orders already allocated.

What it means

It is not the same as physical stock. A warehouse may hold 500 units, but 420 are already promised to other customers, leaving 80 to promise. Salespeople use it to give a delivery date without checking with stores each time. Accuracy depends on keeping stock, allocations and incoming purchases up to date.

Example

A cable distributor holds 2,000 metres of 4 core cable, with 1,500 metres promised to existing orders and a further 3,000 metres due from the mill on Friday. For an order of 2,500 metres, the sales team promises 500 now and 2,000 after Friday.

Records and checks

  • Record on-hand stock, allocated quantities, expected receipts with dates and the available figure.
  • Verify with a physical count of fast-moving items and by checking supplier delivery dates.
  • The stores head keeps stock accurate, and the sales coordinator checks availability before promising.

Common mistakes

  • Promising from physical stock without subtracting quantities already allocated to other buyers.
  • Counting a supplier's delivery as stock before it has arrived and been checked.