Baseline

A baseline is the measured starting level of a metric or process before a change, kept as the fixed reference against which later results are compared.

What it means

Without a baseline, an improvement claim cannot be proved. A baseline should cover a long enough period to include normal ups and downs, and should be measured the same way later. Owners use baselines for scrap rate, delivery performance, cost per unit and collection days, then compare after a change such as a new process or machine.

Example

A packing unit wants to cut rework. It measures three months of rework, finding 6.5 percent of output. After a training programme, rework drops to 4.2 percent over the next quarter, which is a gain measured against the baseline.

Records and checks

  • Record the metric, its definition, the period measured, the data source and the resulting value.
  • Verify that the later comparison uses the same definition, period length and source.
  • The process owner records it, and the finance or operations head approves it as the reference.

Common mistakes

  • Measuring the baseline in an unusually bad or good month, so the later comparison misleads.
  • Changing how the metric is calculated between the baseline and the follow-up.