Bill of quantities

A bill of quantities is a document that breaks a construction or fit-out job into itemised work, each with a description, unit and measured quantity, so that rates can be priced against it.

What it means

It is prepared from the drawings and specifications. Contractors quote a rate per unit for each item, and the total becomes the tender price. During the job, quantities actually done are measured and compared with it. Because it fixes what is priced, it is also used to settle disputes about extras and omissions.

Example

For a 1,000 sq ft office fit-out, the bill lists 85 sq m of vitrified tile flooring, 140 sq m of gypsum false ceiling and 220 sq m of painting. A contractor quotes ₹1,350 per sq m for flooring, giving ₹1,14,750 for that item.

Records and checks

  • Record: item number, description, unit, quantity, rate, amount and the drawing or specification referred to.
  • Verify: quantities against drawings, units against the specification and extensions of quantity times rate.
  • Checked by: the quantity surveyor or engineer prepares it; the owner or project head approves it.

Common mistakes

  • Using vague item descriptions, which lets contractors claim extras later.
  • Measuring quantities in a different unit from the one used for pricing.