Bottleneck

A bottleneck is the step or resource in a process with the lowest capacity, which sets the maximum output of the whole line, however fast the other steps run.

What it means

Work piles up in front of the bottleneck while the stations after it wait for material. Improving anything else does not raise total output; improving the bottleneck does. It can be a machine, a skilled worker, an approval step or even a delivery truck. Finding it means looking for where work waits the longest and which resource is always busy. Once relieved, the bottleneck moves somewhere else.

Example

A Surat embroidery unit cuts 1,200 pieces a day, stitches 700 and packs 1,000. The stitching machines are the bottleneck, with a queue of cut pieces in front of them all day. Adding a second shift on stitching lifts output to 1,000, while adding a cutter would have changed nothing.

Records and checks

  • Record each step's daily capacity, queue size and the hours the resource is actually running.
  • Verify the suspected bottleneck by checking where queues form and where stations sit idle.
  • The production manager monitors it weekly; the owner decides on added shifts or equipment.

Common mistakes

  • Buying faster machines for a step that is not the bottleneck, which only builds more waiting stock.
  • Letting the bottleneck stand idle during breaks or changeovers, which loses output for the whole factory.