Changeover time
Changeover time is the time from the last good piece of one product to the first good piece of the next product on the same machine or line.
What it means
It includes removing old tooling, fitting new, adjusting settings, cleaning and the first trial pieces until quality is acceptable. Long changeovers push firms toward big batches, which raises stock. Shortening them lets a plant make smaller runs and respond faster to orders. Preparing tools and materials before stopping the machine is usually the cheapest improvement.
Example
A plastic moulder takes 90 minutes to change from one container to another. After keeping the next mould heated and ready on a trolley, the changeover falls to 50 minutes, giving 40 more production minutes each time.
Records and checks
- Record start and end of each changeover, the product change and the time of first good piece.
- Verify the end point as the first accepted piece, not the machine restart.
- The operator logs times; the supervisor reviews averages, and quality confirms the first piece.
Common mistakes
- Ending the clock at restart, when the machine is still producing rejects.
- Ignoring searching for tools and materials, which is often the longest step.