CPM, or critical path method, is a scheduling technique that finds the longest chain of dependent tasks in a project, which decides the earliest date the project can finish.

What it means

You list tasks, their durations and which must precede others. Working through the links shows the path with no spare time. Tasks on it are critical: if any slips, the finish date slips. Other tasks have float, meaning room to delay without harm. CPM tells a manager where attention and extra labour will actually save time.

Example

In building a 12-room guest house, foundation (20 days), columns and slab (35), brickwork (25) and finishing (30) form a chain of 110 days. Electrical rough-in has 15 days of float, so a delay there does not move the handover date.

Records and checks

  • Record: task list, durations, predecessors, start and finish dates, float and the critical path.
  • Verify: that durations are realistic, links are complete and the path is recalculated when work changes.
  • Checked by: the planner updates it weekly; the project manager reviews critical tasks.

Common mistakes

  • Forgetting a dependency, so the real critical path is hidden.
  • Never updating the plan, so it no longer shows where time is lost.