Daily progress report

A daily progress report is a short record, filled in every day, of what work was done on a project, with the labour, materials, equipment, weather, delays and issues for that day.

What it means

It gives the office a dated picture of the site and builds evidence for later claims. A good report lists work by activity and quantity, headcount by trade, major materials received or consumed, machinery working or idle, and any stoppage with its reason. It also notes instructions received and safety incidents.

Example

On 14 August, a site report shows 18 masons and 30 helpers, 42 cu m of concrete poured on the second slab, cement received 120 bags, and two hours lost to rain. The next morning the engineer compares it with the target of 50 cu m.

Records and checks

  • Record: date, activities and quantities, manpower by trade, materials, machines, delays and issues.
  • Verify: that quantities agree with measurements and that labour counts match attendance.
  • Checked by: the site engineer signs it daily; the project manager reviews it and the weekly summary.

Common mistakes

  • Filling in reports in bulk at week-end from memory.
  • Leaving out delays and their causes, which weakens any later time claim.