ECO
ECO is short for engineering change order, the approved document that authorises a specific change to a design, parts list or process and states what must be done and from when.
What it means
The request asks whether to change something; the order is the decision and the instructions. It names the affected drawings and parts, the new revision, the effective date and how existing stock and open jobs will be treated. Different departments carry out their share, and the order is closed only when each has confirmed completion. It keeps the factory from drifting into undocumented changes.
Example
A fan maker in Rajkot raises ECO-0147 to change a capacitor from 2.5 µF to 3 µF on the 1,200 mm ceiling fan. It lists the three drawings affected, states the change takes effect from serial 8,000 onward, and instructs stores to return unused old capacitors to the vendor for credit.
Records and checks
- Record the ECO number, reason, affected items, new revisions, effective point and approvals.
- Verify that every affected drawing, list and instruction is updated before the order is closed.
- The engineering head approves; stores, purchasing and production each confirm their action.
Common mistakes
- Closing the order when the drawing is updated but before old stock is dealt with.
- Leaving the effective date vague, so two versions of the product are built in the same week.