Goods receipt note
A goods receipt note is an internal document recording the goods actually received from a supplier, with their quantity and condition, compared to the order.
What it means
Often called a GRN, it is made by the stores or receiving staff on arrival. It states what was delivered, how much, whether it was in good order and which purchase order it relates to. It is the evidence that you should pay for the goods. Accounts compares it with the supplier's invoice and the purchase order before booking and paying; when they differ, the lower of the order and the receipt is generally accepted until resolved.
Example
A purchase order is for 500 kg of resin. The supplier's truck delivers 480 kg. The GRN records 480 kg received, so only 480 kg is approved for payment.
Records and checks
- Record the GRN number, date, supplier, PO reference, quantity received, condition and receiver's name.
- Verify the counted quantity against the delivery challan and the order.
- Stores prepares it; accounts uses it, and no bill is paid without it for stock items.
Common mistakes
- Writing the ordered quantity on the GRN without counting what arrived.
- Raising GRNs days after receipt, so shortages cannot be proved.