Kerf

Kerf is the width of the slot of material removed by a saw blade, laser beam, plasma arc or other cutting tool as it passes through the workpiece.

What it means

Every cut takes away a thin strip, so the pieces on either side are slightly smaller than the stock they came from. Kerf width differs by process: a band saw removes a few millimetres, a plasma cut perhaps 1.5 to 3 mm, and a laser much less. Programmers compensate for kerf in the cutting path so parts finish at the drawn size.

Example

A bar of 1,000 mm is cut into equal pieces with a 3 mm saw kerf. Nine cuts remove 27 mm of material, so cutting ten 100 mm pieces needs 1,027 mm.

Records and checks

  • Record the cutting method, blade or nozzle type, the kerf value used and the material thickness.
  • Verify the kerf by measuring a test cut, and again after changing the blade or nozzle.
  • The machine programmer sets the compensation, and the operator reports any size drift.

Common mistakes

  • Using one kerf figure for all thicknesses, when kerf grows with thickness and blade wear.
  • Leaving it out of material estimates, which understates the stock needed.