Operation bulletin

An operation bulletin is the document listing each sewing operation of a style, with its sequence, machine, SMV and number of operators, used to set up and balance a line.

What it means

It builds on the operation breakdown by adding the manpower and target per hour for each operation. The line is then arranged so work flows with no long waits, and each operator's work matches their skill. It also helps compute piece-rate. When the style or an operator changes, the bulletin is revised.

Example

A kidswear style has an OB of 24 operations and total SMV of 9.6. For a daily target of 1,000 pieces on a line of 30, the engineer sets two operators on the 1.0 minute operation to avoid a bottleneck.

Records and checks

  • Record sequence, operation, machine, SMV, operators and target per hour.
  • Verify that line layout and operator skills match the bulletin.
  • The industrial engineer prepares it; the line supervisor follows it.

Common mistakes

  • Setting a target without balancing the line first.
  • Not revising the bulletin after a style change or buyer comment.