Order acknowledgement
An order acknowledgement is the seller's written confirmation to the customer that an order has been received and accepted, stating items, quantities, price, terms and delivery date.
What it means
It closes the loop on the purchase order. By repeating what the seller understood, it lets the customer catch any mismatch early, such as a wrong specification or date. It also fixes the confirmed delivery date. Where the seller cannot meet any term of the order, the acknowledgement states what differs.
Example
A buyer orders 1,000 packing cartons. The supplier's acknowledgement confirms the size and price, but gives delivery in 12 days against the 8 requested. The buyer replies within a day to agree, and the date is locked for planning.
Records and checks
- Record the order number, acknowledgement date, accepted terms, any differences and the confirmed delivery date.
- Verify the acknowledgement against the customer's order line by line before sending it.
- The sales coordinator sends it, and the customer's reply is filed with the order.
Common mistakes
- Sending an acknowledgement that only says "order received" without the terms that matter.
- Not checking the customer's reply, so a disagreement surfaces only at delivery.