Overall equipment effectiveness
Overall equipment effectiveness (OEE) is a percentage that multiplies availability, performance and quality to show how much of a machine's planned time produces good parts at the rated speed.
What it means
OEE tells a plant owner how well a machine is really used. Availability is run time divided by planned production time. Performance is actual output divided by what the machine could make at its rated speed in that run time. Quality is good pieces divided by total pieces. The weakest factor shows where to start.
Example
A press is planned for 8 hours, runs 6 hours, makes 2,400 pieces against a rated 3,000, and 2,280 are good. Availability is 75%, performance 80%, quality 95%, so OEE is about 57%.
Records and checks
- Record planned hours, stop minutes with reasons, total pieces and rejected pieces for every shift and machine.
- Verify that the rated speed comes from the process sheet and not from a figure the operator finds convenient.
- The supervisor reviews each shift, and the plant head reviews weekly.
Common mistakes
- Counting planned stops such as lunch or scheduled maintenance as lost availability, which makes every machine look worse than it is.
- Using an easy rated speed, so performance always shows near 100% and hides real slowdowns.