Production plan
A production plan is a schedule setting out what products will be made, in what quantities and when, balanced against demand, stock and available capacity.
What it means
It translates expected sales into work for the factory. You start with demand, from orders and forecast, subtract the finished stock you hold, and plan the quantity to be made each week, within what the machines and people can do. The plan also shows the materials needed and sets a target for output. It is reviewed regularly, as demand and capacity rarely stay as expected.
Example
A Tiruppur sock manufacturer expects to sell 24,000 pairs next month and holds 5,000 pairs in stock. It plans to make 19,000 pairs, with 4,750 a week, within its capacity of 5,200. The plan then tells purchasing to book 3 tonnes of yarn and tells the dyeing unit to expect about 2 tonnes weekly.
Records and checks
- Record demand, opening stock, planned quantity by period, capacity and materials required.
- Verify the plan against actual output each week, and note the cause of any shortfall.
- The planning head prepares it; the owner approves it and sales confirms it matches commitments.
Common mistakes
- Planning to full theoretical capacity, so every breakdown makes the plan fail.
- Not reviewing it against actual output, so errors repeat month after month.