Queue time

Queue time is the time a job, part or document waits in line before the next operation or action begins on it.

What it means

Work sitting in front of a busy machine, an approval desk or a testing bay is in queue. It adds nothing to the product, yet it often forms most of lead time. Queues form where a step has less capacity than the flow into it, or where work arrives in big batches. Measuring them shows the real bottleneck.

Example

A casting arrives at the machine shop on Monday and is machined on Thursday. It waited three days in front of a busy lathe. The actual machining took 40 minutes, so for this casting about 98 percent of the time in the shop was queue.

Records and checks

  • Record the arrival time at each stage and the time work started on it.
  • Verify with scan times or job cards that queue time is captured at each stage.
  • The planner reviews queues weekly, and the production head adds capacity or changes batch sizes where they are longest.

Common mistakes

  • Assuming the slowest machine is the bottleneck without measuring where jobs actually wait.
  • Releasing too many jobs at once, which lengthens every queue.