RA bill

An RA bill is the short form of running account bill, an interim bill that a contractor raises for work done to date, with earlier payments and deductions adjusted.

What it means

On site, people say "RA bill 3" to mean the third interim bill. It is a cumulative bill: it shows the total value of work done up to now, subtracts what has already been billed in earlier RA bills and shows only the difference as the current claim. Retention and advance recoveries are taken out before the net payable figure.

Example

Up to the third RA bill, a contractor has done ₹18 lakh of work. The earlier two bills totalled ₹11 lakh, so this bill claims ₹7 lakh gross. After 5 per cent retention of ₹35,000 and an advance recovery of ₹70,000, the net payable is ₹5,95,000.

Records and checks

  • Record: RA bill number, period, cumulative work done, previous bills, deductions and net payable.
  • Verify: that quantities agree with the measurement book and that previous bill figures are carried forward correctly.
  • Checked by: the site engineer certifies; the accountant verifies deductions; the project head approves payment.

Common mistakes

  • Billing the same measured quantity twice across successive bills.
  • Forgetting to carry forward advance and retention balances.