Retention money
Retention money is a percentage of each contractor payment that the client holds back as security, to be released after completion or after the defect-correction period ends.
What it means
It motivates the contractor to finish snag lists and repair defects, because the money is only released afterwards. The percentage and release conditions are set in the contract, often half on completion and half after a defects period. For the contractor, it is an amount earned but not yet received, so it should be tracked separately in receivables.
Example
A client withholds 5 per cent from every bill on a ₹50 lakh contract, holding ₹2.5 lakh by the end. Half is released at handover. The remaining ₹1.25 lakh is released a year later, after the contractor repairs two leaking joints during the defects period.
Records and checks
- Record: contract percentage, amount held from each bill, cumulative balance, release conditions and dates.
- Verify: that deductions in each bill agree with the contract and that the cumulative balance is correct.
- Checked by: the accountant tracks the balance; the project head confirms completion before release.
Common mistakes
- Forgetting to ask for release when the defects period ends, leaving money locked up.
- Releasing retention before defects are cleared, and losing the leverage.