Supplier capacity

Supplier capacity is the quantity of goods or work a supplier can reliably produce and deliver in a given period.

What it means

A supplier may claim a large number, but what matters is what is left for you after its other customers, machine breakdowns and labour shortages. Buyers ask about shifts, machines, raw material stock and the current order book. Knowing this before a big order avoids partial deliveries later.

Example

A toy maker needs 20,000 moulded parts in a month. The mould shop says it can run 25,000, but on a visit the buyer finds only one of two machines working and half its time already booked. Real capacity is near 9,000, so the buyer splits the order with a second shop.

Records and checks

  • Record the stated capacity, the machines and shifts behind it, and the date confirmed.
  • Verify by a visit, a call to the shop floor or past deliveries against promises.
  • The purchase head checks it before any order that is large for that supplier.

Common mistakes

  • Taking a phone assurance as proof and never asking how much capacity is already booked.
  • Placing the festival-season order late, when every supplier is full.