Supplier lead time
Supplier lead time is the number of days from placing a purchase order until the goods are received and ready to use in your store.
What it means
Lead time decides how early you must order. It includes the supplier's processing or production time, transport, and your own unloading, inspection and booking-in. Real lead time varies, so careful buyers track the usual figure and the worst recent one. A supplier who quotes seven days but averages eleven forces you to hold extra cushion stock.
Example
A packaging buyer orders corrugated boxes on the 3rd and receives them on the 12th. The nine-day lead time, against a quoted six, means the reorder level must cover at least nine days of use plus a safety margin.
Records and checks
- Record order date, promised date and actual receipt date for each purchase order line.
- Verify average and longest lead time per supplier before setting reorder points.
- The purchase officer maintains the dates; the owner reviews supplier delivery performance.
Common mistakes
- Using the supplier's quoted lead time without comparing it to what happened on past orders.
- Counting only transit and forgetting inspection and booking-in days at your own gate.