Unplanned downtime

Unplanned downtime is the time a machine or line is not producing when it was scheduled to, because of breakdowns, material shortages, power cuts or similar unexpected causes.

What it means

It differs from planned downtime, such as scheduled maintenance, tea breaks or changeovers, which are expected and built into the schedule. Tracking each stop's cause and duration shows which few causes repeat.

Example

A packaging unit scheduled a machine for 200 hours in a month and lost 24 hours: 10 to a sealing-bar failure, 9 waiting for film rolls and 5 to power cuts. The owner sees that 19 of 24 hours were avoidable by a spare bar and better film ordering.

Records and checks

  • Record the start time, end time, machine, cause code and the corrective action for every stop.
  • Verify that totals reconcile to scheduled hours minus run hours for each machine.
  • The operator logs each stop, the maintenance lead reviews the cause list weekly, and the plant head acts on the top three.

Common mistakes

  • Logging every stop as "machine problem", which hides the real causes.
  • Leaving out short stops of a few minutes, which often add up to more lost time than breakdowns.