Design-to-launch: daily operating review pack

This is a short daily sheet for the people working on a new product or service launch. It brings design tasks, samples, test results, supplier material and cost into one view, so the project lead can see what is blocking the launch date and who must act today.

When to use it

Use it every working day while a launch is active, from the day the specification is fixed until the first lot or first customers are served. Stop the daily review once the launch is done and move to a weekly one.

The template

WorkstreamWhat to enterSource recordAction triggerOwner
Design tasksTasks due today, number finished, any waiting for a decisionTask listA task past its due dateDesign lead
Change requestsNew requests received, and whether each was approved or heldChange logA change after the specification was fixedProject lead
Samples and trialsWhich sample or trial is in progress and its stageSample trackerA trial not started on its planned dateOperations head
Test resultsTests finished, tests waiting, and any measurement outside the agreed rangeTest recordsAny result outside rangeQuality lead
Material and supplierItems due, items received, and expected arrival datesPurchase orders, supplier messagesMaterial due within a few days but unconfirmedPurchase lead
Cost against targetCurrent cost per unit in ₹ against the target in ₹Costing sheetCost above targetAccounts lead
Days to launchDays left to the planned date and the date you now expectLaunch planExpected date later than plannedProject lead
Open issuesIssues without a named owner or without a dateIssue listAny issue with no ownerProject lead

How to fill it

  • What to enter: counts, dates and rupee values, with a three or four word note when something is out of range.
  • Source record: state which list you took each line from, so the same line can be rebuilt the next day.
  • Action trigger: set your own triggers at the start of the project and note them in this column. They belong to your team, and should not change midweek.
  • Owner: the person who explains the line in the huddle.
  • Add one line at the bottom for the single decision needed today and who will take it.

Example row

WorkstreamPlannedActualNoteOwner
Cost against target₹140 per unit₹146 per unitPackaging quote rose from ₹6 to ₹10; asking two other suppliers for rates by ThursdayAccounts lead

Review and sign-off

  • The project lead runs the review and initials the sheet, and the owner reads the week's sheets on a fixed day.
  • Review daily during the launch, and look at the week's pattern every Friday for lines that were red more than twice.
  • Escalate to the owner on the same day when the expected launch date slips, when cost goes above target, or when a failed test needs a design change.

Keeping it up to date

  • Remove workstreams that are finished and add any that the project newly needs, such as a trial run at a second site.
  • Carry the last week's sheets into the launch review so the cause of each delay is on record.
  • Keep the sheets for the period your CA or the law requires, as they support project cost and decision records.