Plan-to-deliver: control and audit worksheet
This worksheet lets an operations manager or owner test whether the planning routine is actually being run, from the demand forecast to the next-day huddle. Instead of sampling orders, you sample working days and look for the plan, the capacity record and the progress notes for each one. It suits factories, workshops and service firms where plans are made but rarely checked.
When to use it
Use it monthly on three or four working days chosen at random, and after a week in which output or service promises slipped badly. It is also a useful handover check when a new planner or shift supervisor starts.
The template
| Control | What to test for the sampled day | Evidence to pull | Reviewer | Result and note | Corrective action |
|---|---|---|---|---|---|
| Demand forecast made from records | Forecast quantity can be traced to sales orders, past dispatches or booked appointments | Demand forecast | Operations manager | ||
| Required and free capacity compared | Capacity board shows people, hours and equipment for the day, including known leave | Capacity board | Operations manager | ||
| Dated schedule built and clashes resolved | Each job has a date, an owner and a resource, with no double booking | Daily plan | Shift supervisor | ||
| Attendance reflected in the plan | People marked absent were removed from capacity before work was allocated | Attendance, capacity board | Shift supervisor | ||
| Daily progress and slippage captured | Planned and actual output are both recorded, with a reason for any gap | Daily plan, progress notes | Planner | ||
| Next-day huddle held | Decisions are written down with owners and dates | Huddle decisions | Shift supervisor |
How to fill it
- Control: keep to the routine your business really follows. Delete a line rather than leave one that is never tested.
- What to test for the sampled day: one comparison per line, such as planned quantity against the forecast.
- Evidence to pull: the actual sheet or record for that date. A plan reconstructed later does not count.
- Result and note: write met, partly met or not met, then the date tested and what you saw. Where the line touches working hours, overtime or leave rules, check the current rule on the official portal or with your CA before acting.
- Corrective action: one action, one owner and one date. If the same gap appears on several sampled days, make the action about the routine, not the day.
Example row
| Control | Sampled day | Result and note | Corrective action |
|---|---|---|---|
| Attendance reflected in the plan | 10/11/2026 | Partly met. 2 of 14 operators were absent but the plan still used all 14, so 16 operator hours were over-planned | Shift supervisor to update the capacity board before 9 am each day. Retest on 24/11/2026 |
Review and sign-off
- The owner reviews the completed worksheet. The planner and shift supervisor should not review their own routines.
- Run it monthly, and keep the same controls so months can be compared.
- Escalate to the owner when a control is not met on two sampled days in a row, or when a plan was found to be built without a capacity check.
Keeping up to date
- Keep each worksheet with the plans and boards it tested for the period your CA or the law requires.
- Add a control line when you introduce a new step, such as a weekly material check.
- Never overwrite an earlier result. Add the date the corrective action was closed and what evidence showed it.
Did not find your answer?Message the lamp team on WhatsApp. Ask about setup, your records, or anything we have not covered here.Ask us on WhatsApp →