APQP is the short name for advanced product quality planning, a framework of five planned phases that takes a new part from concept to a proven, controlled production process.

What it means

Suppliers to vehicle and equipment makers are often asked to follow APQP when they take on a new part. The five phases are planning, product design, process design, product and process validation, and then production with feedback. At each stage the team produces documents and has them reviewed against a timetable. Small firms use it by keeping the steps in proportion to the part's risk, not by copying a heavy template.

Example

A Pune sheet-metal firm is asked by an auto customer to follow APQP for a brake bracket. It sets a 14-week schedule, assigns one person per phase, and holds a gate review at weeks 4, 8 and 12 with the customer's engineer, who needs to see risks closed before the trial run.

Records and checks

  • Record the phase schedule, owners, deliverables and the minutes of each review.
  • Verify that the deliverables match what the customer's requirements specify before each gate.
  • The quality head checks completeness; the customer representative accepts the phase outputs.

Common mistakes

  • Running the five phases in strict sequence with no overlap, so a late design change forces a restart.
  • Producing documents for the audit but not keeping them updated when the process changes.