BOQ

BOQ is the short form of bill of quantities, the priced list of work items with units and quantities that forms the basis of a construction tender and contract.

What it means

On site, "BOQ" refers to the working sheet itself: numbered items, quantity, rate and amount, often with the contractor's rates filled in. The same sheet later becomes the base for running bills, because each measured item is compared against its BOQ quantity. An item not in the BOQ is usually treated as extra work and needs a separate rate and approval.

Example

A contractor's BOQ for a warehouse shed has item 4.2, "RCC footing M20, cubic metre", 36 cum at ₹7,400, amount ₹2,66,400. In month one, 20 cum is measured, so 56 per cent of the item is billed.

Records and checks

  • Record: item number, description, unit, BOQ quantity, rate, quantity done so far and balance.
  • Verify: that billed quantity never exceeds the BOQ quantity without an approved variation.
  • Checked by: the site engineer measures, the billing engineer updates and the project manager approves.

Common mistakes

  • Treating a BOQ item as complete because the budget is spent, not because the quantity is done.
  • Adding extra work in the field without a recorded change to the BOQ.