Call-off order

A call-off order is a specific delivery request, giving quantity and date, raised against an existing contract or blanket order that already fixes the price and terms.

What it means

The main agreement settles price and conditions. When goods are actually needed, the buyer sends a call-off. It is short and tells the supplier what to deliver, where and when. It does not renegotiate anything. Each call-off reduces the balance on the main order. It helps the buyer hold less stock, since deliveries can follow actual production, while the supplier plans against a known commitment.

Example

A Bengaluru electronics assembler holds a yearly agreement for 120,000 connectors at ₹4.80 each. On 3 June, it sends a call-off for 10,000 pieces to be delivered by 17 June. The supplier ships on the 15th and invoices ₹48,000, and the balance on the agreement falls to 110,000.

Records and checks

  • Record the call-off number, linked agreement, quantity, delivery date, place and balance remaining.
  • Verify that the receipt matches the call-off quantity and that the invoice uses the agreed price.
  • Production planning raises it; stores checks receipt, and purchasing monitors the remaining balance.

Common mistakes

  • Sending calls with too short a notice for the supplier's lead time, then blaming late delivery.
  • Not updating the balance after receipts, so the commitment runs out unnoticed.