Capable to promise
Capable to promise is a delivery commitment based on what the business can produce in time, taking material, capacity and lead time into account, as well as existing stock.
What it means
Available to promise looks at stock and incoming supply. Capable to promise goes further for a make-to-order business: it asks whether raw material can be arranged and whether the machines and people have free time before the date the customer wants. It gives a realistic date, instead of a hopeful one.
Example
A switchgear maker is asked for 40 panels in three weeks. It checks the copper bar stock, finds enough, but sees the assembly bay is booked for 2 weeks with other work. It promises delivery in 4 weeks instead, avoiding a missed date.
Records and checks
- Record the order quantity, material availability, free capacity by week and the date promised.
- Verify the capacity and material figures with the planner and store before confirming the date.
- The planner works it out, and the sales head confirms it to the customer.
Common mistakes
- Promising the date the customer wants without checking free capacity.
- Counting a machine's full hours as available when it is also needed for maintenance and other jobs.