Capacity requirements planning
Capacity requirements planning is the calculation of machine and labour hours needed to complete planned orders, compared with the hours actually available in each period.
What it means
After production orders are planned, you ask whether the shop can do them. Each order is translated into hours at each work centre using its routing. Totals per week are set against the hours available. Where need exceeds capacity, you can add shifts, outsource, move dates or reduce the load. It follows from material planning and checks whether that plan is realistic.
Example
A Rajkot gear shop has two hobbing machines, giving 96 machine hours a week after maintenance. Next week's orders need 130 hobbing hours. The planner moves 20 hours of a flexible order to the following week and sends 14 hours to a nearby job-work unit.
Records and checks
- Record the available hours per work centre, the required hours per order and the weekly gap.
- Verify that routing times reflect real run and setup times, not ideal figures.
- The planner prepares it; the production head approves the action for each overloaded week.
Common mistakes
- Counting every scheduled hour as available, ignoring breakdowns, breaks and maintenance.
- Using outdated routing times, so the plan looks feasible while the floor is overloaded.