lamp.
ResourcesPricingAbout

Change request

A change request is a formal, written proposal to alter something already agreed in a project, such as its scope, cost, schedule or specification.

What it means

Projects rarely run exactly as planned. The client may want a different finish, or the site may reveal a problem. A change request records what is to change, why, and what it does to cost and time, and nothing proceeds until the person with authority has approved it. This stops quiet scope growth and later arguments about who agreed to what.

Example

A client asks a builder to move a partition and add two sockets. The change request estimates ₹38,000 extra and two more days. The client signs it, the schedule and budget are updated, and the extra is added to the next bill.

Records and checks

  • Record: request number, date, requester, description, reason, cost and time impact and the decision.
  • Verify: that impact figures are based on actual rates and that the change is reflected in the budget and schedule.
  • Checked by: the project manager assesses; the client or the owner approves in writing.

Common mistakes

  • Carrying out verbal changes first and discussing the cost afterwards.
  • Approving without checking the effect on the completion date.
Did not find your answer?Message the lamp team on WhatsApp. Ask about setup, your records, or anything we have not covered here.Ask us on WhatsApp →