Control plan
A control plan is a document listing, for each process step, the characteristic to control, the method and frequency of checking, the limits and the action when a result is outside them.
What it means
It sits between the process flow and the shop floor. For each step it names the part feature or process setting that matters, the gauge to use, how many pieces to check and how often, and what the operator does if the reading is off.
Example
A turning shop makes a shaft with a 25.00 mm journal, tolerance plus or minus 0.02. The control plan says the operator measures five pieces with a micrometer every hour. If any piece is outside the limit, the operator stops, segregates the hour's output and calls the supervisor.
Records and checks
- Record characteristics, specifications, gauges, sample size, frequency and reaction plan.
- Verify that operators know the plan and that gauges are within calibration.
- The quality engineer owns it, and the production head signs it.
Common mistakes
- Writing it once for approval and never updating it after a process change.
- Listing a check but no reaction plan, so a bad reading leads to no action.