Drawing revision
A drawing revision is a new, identified version of an engineering drawing, issued after a change in shape, size, tolerance, material or notes, with the old version withdrawn.
What it means
Each drawing carries a revision letter or number and a short note of what changed. When a change is approved, the drawing is reissued under the next revision, and every holder of the old copy is told to stop using it. Shops, vendors and inspectors must all work from the same latest revision, because making parts to an old one produces scrap that looks perfectly good.
Example
A Faridabad tool room machines a bush from drawing D-204 Rev C with a bore of 24.00 mm. The customer approves a change to 24.02 mm, issued as Rev D on 6 May. The shop-floor copy is swapped, the old copy is stamped withdrawn, and the supplier of the heat treatment is informed.
Records and checks
- Record the revision, date, change description, approver and the list of people who received it.
- Verify that the shop floor, stores and vendors hold only the current revision before work starts.
- The design office issues it; the quality inspector checks the revision on the job card matches.
Common mistakes
- Marking changes by hand on a copy, so no controlled revision exists for anyone else.
- Not recalling old prints, so vendors keep making parts to the earlier dimension.