Expediting

Expediting is the follow-up of open purchase orders or jobs to make sure they arrive or finish by the promised date, by chasing, visiting or reprioritising.

What it means

When an order is at risk, someone calls the supplier, finds the cause of delay and pushes for action: a partial shipment, a faster transport mode or priority on the supplier's line. Inside the factory, expediting means moving a job ahead of others. It is a normal task for urgent items, but if it is needed all the time, the planning is weak or lead times are wrong.

Example

A Pune machine builder is waiting for a ₹3.2 lakh gearbox due on Monday, with assembly scheduled to start Tuesday. On Thursday, the buyer calls and learns the gears are waiting for heat treatment. He asks for a partial dispatch of the housing and ships a rush heat-treatment batch, so the gearbox arrives Tuesday morning.

Records and checks

  • Record the order, promised date, each follow-up date, the contact, the reason for delay and the outcome.
  • Verify the status of key orders a few days before the due date, not on it.
  • The buyer follows up; the purchase head steps in for repeated delays and records the vendor's score.

Common mistakes

  • Chasing only when a delivery is already late, instead of a few days before.
  • Expediting every order, so true emergencies are indistinguishable from routine follow-up.