Firm planned order

A firm planned order is a planned production or purchase order that has been fixed by a planner in quantity and date so that automatic planning runs will not alter it.

What it means

Material planning normally recalculates its suggestions each time demand changes, moving or deleting them. Sometimes a human knows better: a long-lead material must be ordered now, or a machine slot has already been agreed. Firming locks that order in place. The plan then works around it, and it stays until the planner converts it to a real order or releases the lock.

Example

A Mumbai electronics assembler needs imported connectors with a 10-week lead time. The planner firms an order of 8,000 pieces for release on 12 March, even though a forecast revision suggests only 6,500. Because the supplier needs a booking, the planner avoids the plan shrinking the quantity before the order is placed.

Records and checks

  • Record the item, quantity, date, the reason for firming and the planner's name.
  • Verify each firmed order at regular reviews, and release the lock when the reason ends.
  • The planner firms them; the production or purchase head approves large or long-term locks.

Common mistakes

  • Firming orders and forgetting them, so excess stock builds as demand changes.
  • Firming too many orders, which turns the planning system into a list no one can adjust.