Issue to contractor
An issue to contractor is a record of materials, such as cement or steel, that the owner or main builder supplies from its own store to a contractor for use in the work.
What it means
In many contracts the contractor provides labour while the client supplies certain materials. Each handover is recorded, usually on an issue slip signed by both sides. The issued quantity is later reconciled against what the work should have consumed, and the cost of any excess or wastage can be recovered from the contractor's bill as set out in the contract.
Example
A builder issues 200 bags of cement at ₹380 and 2 tonnes of steel to a plastering contractor in March. Later, the work measured needed 175 bags. The extra 25 bags worth ₹9,500 are checked and recovered from the next running bill.
Records and checks
- Record: issue slip number, date, material, quantity, rate, work location and receiver's signature.
- Verify: that issues are within the approved requirement and are later reconciled with work done.
- Checked by: the storekeeper issues; the site engineer approves; the accountant recovers from bills.
Common mistakes
- Issuing materials on verbal requests with no signed slip.
- Skipping reconciliation until the contract ends, when excess can no longer be traced.