Manpower deployment
Manpower deployment is the planned assignment of workers, by trade and number, to specific tasks, sites or shifts so that the work gets done on schedule.
What it means
On a project, it means having the right number of masons, carpenters, helpers and supervisors at each location on each day. Too few slows work; too many raises cost and crowds the site. Planning it ahead from the schedule and quantities, and recording the actual headcount daily, lets you compare plan with reality and wage costs with output.
Example
For a slab casting on Saturday, a site manager plans 12 masons, 25 helpers, 4 carpenters and 2 supervisors. On the day, only 9 masons come. The shortfall is noted, three helpers are re-assigned to masonry support, and the pour finishes two hours late.
Records and checks
- Record: date, location, trade, planned and actual numbers, contractor and hours worked.
- Verify: that headcount in reports matches the attendance sheet and the wages paid.
- Checked by: the supervisor records; the site engineer compares plan against actual daily.
Common mistakes
- Paying for the planned number of workers rather than those actually present.
- Moving workers between tasks without recording it, so costs land on the wrong job.