MB
MB is the common short form of measurement book, the official record in which the dimensions and quantities of work done are written down and signed before payment is made.
What it means
Site staff say "enter it in the MB" or "MB entry done". A measurement of an item, say flooring in a room, is taken with the contractor present, written with length, breadth and result, and signed by both parties. Payment bills then refer to these MB pages, so a mistake in the entry becomes a mistake in the payment. It also protects against later claims.
Example
Tile work in three flats is measured on 8 June. The MB entry reads: Flat 101, 5.2 m by 3.8 m = 19.76 sq m; Flat 102, 18.40 sq m; Flat 103, 21.10 sq m; total 59.26 sq m. The engineer and contractor sign, and the figure flows to the next bill.
Records and checks
- Record: date, item, location, length, breadth, height, calculated quantity, page number and both signatures.
- Verify: calculations again independently and that quantities agree with drawings and the BOQ.
- Checked by: the site engineer measures; a senior engineer or the accountant checks before the bill is passed.
Common mistakes
- Entering quantities from the contractor's claim rather than from actual measurement.
- Leaving blank lines or pages, where figures can be added later.