Mean downtime

Mean downtime is the average length of time a machine is unavailable each time it stops, counted from the stoppage until it is running normally again.

What it means

It adds up total downtime and divides by the number of stoppages. Unlike mean time to repair, which looks only at hands-on fixing, mean downtime also includes waiting for the technician, for spares and for approval. If it is much longer than the repair time itself, the delay lies in support, not in the repair skill. Reducing it raises the machine's availability.

Example

In a month a filling machine stops 8 times, losing 36 hours in total. Mean downtime is 4.5 hours, though technicians report that actual repair work averages only 1.5 hours, so waiting for spares is the main loss.

Records and checks

  • Record stoppage start, technician arrival, repair finish and restart times for each event.
  • Verify the totals against shift logs, and split waiting time from repair time.
  • The production supervisor logs the times; the maintenance head reviews the average monthly.

Common mistakes

  • Using only repair time and overlooking the waiting that actually costs the most.
  • Leaving out short stoppages, so the average appears better than it is.