Mobilisation advance

A mobilisation advance is an upfront payment made by a client to a contractor, before much work is done, to cover set-up costs, and recovered from later bills.

What it means

The contractor needs money to bring in labour, machinery, site offices and materials before the first bill is due. The client may agree a percentage of the contract value, often against a bank guarantee. The contract states how it will be recovered, commonly as a fixed percentage deducted from each running bill until cleared. It is a loan against future work, not extra income.

Example

On a ₹80 lakh contract, the client pays a 10 per cent advance of ₹8 lakh against a bank guarantee. Each running bill has 20 per cent deducted until the ₹8 lakh is recovered. On a first bill of ₹10 lakh, ₹2 lakh is recovered.

Records and checks

  • Record: contract value, advance percentage, date paid, guarantee details, recovery rate and balance outstanding.
  • Verify: that recoveries are deducted in every bill and the balance reaches zero before completion.
  • Checked by: the accountant tracks the balance; the project head confirms the guarantee is valid.

Common mistakes

  • Forgetting to recover the advance in early bills, so a large balance remains at the end.
  • Paying the advance without security, leaving the client exposed if the contractor stops.