MRP II

MRP II is manufacturing resource planning, a development of material requirements planning that also plans capacity, shop-floor activity and the money involved in one connected process.

What it means

The second M stands for resources, not just materials. In practice, it ties together the sales and operations plan, the master schedule, material planning, capacity planning, shop-floor control and costing. It was created because a material plan can look perfect yet be impossible if the machines or cash are not there. The approach is widely used in discrete manufacturing and informs how modern planning is organised.

Example

A Faridabad forging company converts a ₹1.2 crore export order into plans. The material plan shows a need of 38 tonnes of steel. The capacity plan shows the forging press is over by 22 hours in week 5, and the cost plan shows the steel purchase will need ₹32 lakh in working capital. All three are resolved before the order is accepted.

Records and checks

  • Record the linked plans for sales, schedule, material and capacity, with the date of each revision.
  • Verify that a change in one plan has been carried into the others before the meeting ends.
  • The planning head coordinates it; the owner and department heads sign the monthly plan.

Common mistakes

  • Treating it as a software purchase, when the weekly planning discipline is what makes it work.
  • Planning finance separately, so the order is accepted although the cash is not available.