Performance bank guarantee

A performance bank guarantee is a written undertaking from a bank to pay the client up to a stated sum if the contractor fails to perform the contract as agreed.

What it means

The contractor asks its bank to issue it, and pays a fee. The client holds it as security instead of cash, usually for a small percentage of the contract value. It has an amount, a validity date and conditions for a claim. If the work takes longer than planned, the guarantee must be extended before it expires, or the client loses its protection.

Example

A contractor wins a ₹60 lakh road job, and the client asks for a 5 per cent guarantee: ₹3 lakh, valid for 18 months. The work runs late, so the client reminds the contractor two months before expiry to get the bank to extend it.

Records and checks

  • Record: guarantee number, bank, amount, issue and expiry dates, the contract covered and the claim conditions.
  • Verify: that the wording matches the contract and that the bank's issuing branch confirms it is genuine.
  • Checked by: the accountant diarises expiry dates; the project head decides on extension or release.

Common mistakes

  • Letting a guarantee lapse because the expiry date was never diarised.
  • Accepting a guarantee whose wording is different from what the contract demands.