Project baseline

A project baseline is the approved version of a project's scope, schedule and cost, which is kept fixed so that actual progress and spending can be compared against it.

What it means

Without a fixed reference, you can never say whether you are ahead or behind. After the plan is agreed, you save it as the baseline. As work continues, you update a separate current forecast, and the difference between the two shows variance. The baseline changes only through an approved change request, so that late projects cannot quietly redefine "on time".

Example

A hotel renovation is baselined at ₹1.2 crore and 150 days. In week 10, the forecast shows ₹1.28 crore and 162 days. The owner sees the overrun clearly: ₹8 lakh and 12 days, and asks for the cause before approving more.

Records and checks

  • Record: baseline scope, schedule dates, budget, the date approved and every approved change to it.
  • Verify: that forecasts are compared against the baseline and not against revised numbers.
  • Checked by: the project manager maintains it; the owner approves any rebaselining.

Common mistakes

  • Updating the baseline every time something slips, which hides the slippage.
  • Setting it before the scope is firm, so it is useless from the start.
Did not find your answer?Message the lamp team on WhatsApp. Ask about setup, your records, or anything we have not covered here.Ask us on WhatsApp →