Project milestone
A project milestone is a significant checkpoint in a project, such as a design approval, a delivery or the completion of a stage, marking progress rather than work effort.
What it means
A milestone has no duration; it is a moment when something specific is achieved. Typical ones are "drawings approved", "machines delivered" and "trial run complete". They give the owner and client simple points to check progress and decide whether to continue. They are also used to release payments or trigger the next stage, though a milestone need not carry a payment.
Example
For a new packaging line, the milestones are: order placed with the machine maker on 5 March, machine delivered on 20 May, installation complete on 10 June and trial run accepted on 25 June. On 20 May the machine has not arrived, so the owner asks the supplier for a revised date.
Records and checks
- Record: milestone name, planned date, forecast date, actual date and the evidence that it was reached.
- Verify: that each milestone is defined by a result that can be checked.
- Checked by: the project manager reports status weekly; the owner reviews missed milestones.
Common mistakes
- Calling a task a milestone, such as "work on foundation", with no way to say when it is done.
- Moving a milestone date without recording why.