Resource loading

Resource loading is the process of assigning the people, machines and materials a project needs to each task over time, to see how much of each is needed when.

What it means

When you put resources against the schedule, you often find that too much is needed in the same week, say three concrete mixers where only two exist. Loading shows peaks and idle periods. You can then level the load by shifting non-critical tasks within their float, hiring extra, or accepting a later finish. It links the schedule to what is really available.

Example

A contractor's schedule needs 14 carpenters in week 6 and 4 in week 7, but only 10 are on the payroll. By moving tasks with float, the manager spreads the need to 9 or 10 over three weeks and avoids hiring 5 temporary carpenters at a premium.

Records and checks

  • Record: task, resource type, quantity needed per period, availability and cost rate.
  • Verify: that loaded demand does not exceed capacity in any week, and that rates are realistic.
  • Checked by: the planner prepares the chart; the project manager approves leveling decisions.

Common mistakes

  • Planning the schedule without checking whether people and machines exist.
  • Levelling by moving critical tasks, which delays the finish date.