Rework percentage
Rework percentage is the number of units that needed correction after a first attempt, divided by the total units produced, shown as a percentage.
What it means
It shows the part of production that is being done twice. Each reworked unit consumes extra labour, machine time and sometimes material, and can delay deliveries. Rework percentage is tracked by product, by process and by shift, so that its cause can be found. It is closely related to first time right, which is its mirror.
Example
A finishing line handles 2,000 garments in a week, and 160 need re-stitching or re-pressing. Rework is 8 percent. At about ₹18 of extra labour per garment, that week's rework cost roughly ₹2,880.
Records and checks
- Record the units produced, units reworked, defect type, extra hours used and cost.
- Verify that each reworked unit is logged, even when fixed on the spot.
- The supervisor logs the counts, and the quality head reviews the causes and the weekly cost.
Common mistakes
- Not counting small fixes done by the operator, which understates the true rate.
- Tracking only the percentage and ignoring the cost behind it.