Schedule attainment

Schedule attainment is the percentage of planned production, by quantity and due date, that was actually completed as scheduled.

What it means

A plant that plans 100 jobs for the week and completes 85 on or before their scheduled day has 85 percent attainment. Defining it by quantity alone can hide lateness, so many plants count a job only when it is completed on time and in the planned quantity. Persistent low attainment suggests unrealistic schedules or frequent disruptions.

Example

A fabrication shop schedules 40 job cards for a week. It completes 31 as planned. The attainment is 77.5 percent. Reviewing the 9 misses shows 5 were held up by missing material, so the planner changes the release rule to check material first.

Records and checks

  • Record the planned quantity and date, the actual quantity and completion date, and the reason for any miss.
  • Verify that completions come from job cards, not from verbal reports.
  • The planner computes it weekly, and the production head acts on the main reasons for misses.

Common mistakes

  • Counting jobs completed late as met, which hides the real performance.
  • Raising attainment by padding schedules with generous time instead of fixing causes.