Scope creep

Scope creep is the slow growth of a project's work beyond what was originally agreed, usually without a matching change in price, time or resources.

What it means

It rarely arrives as one big demand. It arrives as small favours: one extra socket point, one more report, one more design round. Each looks too minor to bill, but together they turn a profitable job into a loss.

Example

A contractor quotes ₹4,20,000 to tile a showroom. During the job the owner asks for a skirting upgrade, two extra niches and a changed pattern in the entrance. The crew works an additional nine days, and none of it is billed because nobody wrote it down.

Records and checks

  • Record every request that is outside the agreed scope, with date, who asked and the rough cost and time impact.
  • Verify each request against the signed scope before the crew starts it, and get written approval for anything extra.
  • The project manager reviews the log weekly and the owner approves chargeable changes.

Common mistakes

  • Agreeing to extras by phone or on site and relying on memory when the final bill is disputed.
  • Treating small additions as free goodwill without counting the labour and material they consume.