Specific energy consumption

Specific energy consumption is the energy used to produce one unit of output, such as kWh per tonne, per thousand pieces or per metre of fabric.

What it means

It ties energy to production so efficiency becomes visible. The figure can be worked for a whole plant, a department or one machine. Benchmarking against past months and similar plants shows where to look. A falling number means better efficiency or a better mix of products. Comparing only like with like matters, because a heavy item takes more energy than a light one.

Example

A fabric processing unit in Surat used 90,000 kWh to finish 450,000 metres in a month, a specific energy consumption of 0.2 kWh per metre. Its target for the next quarter is 0.18 after fixing steam and compressed air losses.

Records and checks

  • Record energy by meter and output by unit for each department, every month.
  • Verify the energy and output belong to the same period and the same boundary of the process.
  • The plant manager reviews the trend, and the owner sets targets with the energy auditor.

Common mistakes

  • Blending different products into one number and drawing the wrong conclusion.
  • Counting output that was made but later rejected.