Variation order
A variation order is a formal, signed document that changes the agreed scope, price or completion time of a contract, covering additions, omissions or substitutions.
What it means
Contracts rarely survive unchanged. Clients change designs, drawings turn out incomplete, and site conditions surprise everyone. A variation order records the change, its rate or lump sum and its effect on the schedule, before the work is billed. It protects the contractor from unpaid extras and the client from surprise charges.
Example
A fit-out contract of ₹18,00,000 includes plain gypsum ceilings. The client later wants a cove lighting profile across 85 running metres at ₹520 per metre. The variation order records ₹44,200 extra and a three-day extension, signed by both before the work starts.
Records and checks
- Record the variation number, description, quantities, rate basis, cost, time effect, approver and date.
- Verify the rate against the contract rate list or a fresh quotation, and confirm the work was actually executed.
- The project manager prepares it and the client or owner signs; accounts adds it to the running bill.
Common mistakes
- Starting the extra work first and chasing approval after, when the client's attitude has changed.
- Not updating the contract value, so the final bill looks inflated to the client.