WBS
WBS is short for work breakdown structure, a hierarchical list that divides a project into smaller deliverables and tasks so each can be estimated, assigned and tracked.
What it means
In daily use, people say "make the WBS" when they want a project turned into a numbered checklist of parts. The top level is the whole job, the next levels are major sections, and the lowest level is a task one person can finish. Every cost, date and owner then attaches to a numbered line, so nothing falls between gaps.
Example
A warehouse shed project is coded 1.0. Under it, 1.1 is foundation, 1.2 is steel structure, 1.3 is roofing, 1.4 is electrical. Under 1.2, task 1.2.3 is column erection with a mason crew and a ₹86,000 budget.
Records and checks
- Record each code, description, owner, planned start and finish, quantity and budgeted cost.
- Verify that the lowest-level lines add up to the whole scope, with no overlaps and nothing missing.
- The project manager builds it and department heads confirm their own sections.
Common mistakes
- Listing activities in the order they happen instead of grouping by deliverable, which hides what is complete.
- Breaking tasks so finely that updating the structure takes more time than the work itself.