WPS
WPS is the common abbreviation for welding procedure specification, the written document that tells a welder the process, materials and settings to use for a given joint.
What it means
On a fabrication floor, people simply say "the WPS" for the approved sheet that goes with the job. It names the joint type, base metal and thickness range, filler and shielding gas, current and voltage range, and any preheat. It is tied to a procedure qualification record showing the settings were proven by test.
Example
A fabricator receives a purchase order for 30 pressure vessel supports. The customer asks for the WPS before work starts. The welding engineer sends the approved WPS, and the customer's inspector signs it off before cutting begins.
Records and checks
- Record the WPS number and revision against each job, along with the welders assigned.
- Verify that the WPS number on the traveller or job card matches the approved document.
- The welding engineer owns it, and the customer's or third-party inspector approves where required.
Common mistakes
- Quoting a WPS number that does not cover the actual material grade used on the job.
- Letting a superseded revision stay in the workshop and be used by a welder.